LATEST NEWS Mann's roar in Majha!, starts AAP's election campaign in Gurdaspur for Shery Kalsi Mann in Amritsar -When the people of Majha make up their minds, they do not sway, this time they have decided to make AAP win Congress will provide 50 percent reservation to women in jobs: Lamba Haryana CEO takes first-of-its-kind initiative, State Voters to receive Wedding-Style Invitations for General Elections Wheat procurement gains pace as agencies procure 334283.4 MT grains Governor Shiv Pratap Shukla presents Road Safety Awards From Siliguri to a Chai Empire: How a Women Entrepreneur Brew a Successful Tea selling brand CHAIOM Science Fest organised at Rayat Bahra University Detaining the colonizer is a highly condemnable act - Gurjit Singh Aujla AIMS Mohali Observes DNA Day Vigilance Bureau Arrests Patwari Accepting Rs 10,000 Bribe For Mutation Of Land Vigilance Bureau Nabs Senior Assistant For Taking Rs 20,000 Bribe Vigilance Bureau Nabs Reader Of Sho Nri Police Station Taking Rs 20,000 Bribe SANY Heavy Industry India Pvt Ltd Expands Presence with Grand Opening of Raghunath Machinery HO in Rayagada, Odisha Ideathon 2K24 held at CGC Jhanjeri, 160 teams from various colleges participated Retailers Discuss Ways to Stay Ahead of the Curve at the RAI Hyderabad Retail Summit 2024 Bobby Deol Drives the Badass Seltos Hyundai Motor Group Executive Chair Euisun Chung Visits India to Underline Mid-to long-term Mobility Strategic Commitments Rupnagar police arrest accomplice of attackers involved in murder of VHP leader Vikas Prabhakar Complete exercise of identifying critical polling stations within this week : Sakshi Sawhney The impact of the Deputy Commissioner Dr. Senu Duggal strictness, a record jump in lifting in two days

 

DDC Anantnag reviews progress of languishing projects

Listen to this article

5 Dariya News

5 Dariya News

5 Dariya News

Anantnag , 18 Dec 2019

The District Development Commissioner, Anantnag, Khalid Jahangir today chaired a meeting of officers of R&B, PHE, PDD, Education, Health, Urban Development Department, Tourism, Irrigation & Flood Control to review the status of languishing projects in the district.The DDC directed the concerned departments to ensure the completion of languishing projects before the targeted timeline as the physical and financial progress of the same is monitored by High Level Committee.The DDC also stressed upon the officers to include other pending under execution projects in languishing lists so that the long pending schemes and projects are taken up for the benefit of public. He stressed for addressing the issues related to scarcity of drinking water, construction of filtration plants, construction and up gradation of road projects under CRF besides expeditiously completion of languishing projects in the district.The SE Hydraulic informed the meeting that Rs.141 crore were sanctioned for 52 projects in the district out of which 12 projects have been completed while six projects will be completed by the end of March, 2020 with a total expenditure of Rs.40 crores.  It was given out that under R&B sector 36 projects with an sanctioned cost of Rs.57.93 crore including 17 road projects and 18 bridges in R&B Sub-Divisions of Anantnag, Vailo & Qazigund have been taken up.

The SE, R&B informed the meeting that the construction of 16 bridges will be completed by the end of 2020 at an expenditure of Rs.11.95 crore. While construction work of shopping complex at Old SRTC Yard being executed by Urban Development Department at an estimated cost of Rs.11.42 crore will be completed by the end of March, 2020.The meeting was informed that under Health Sector construction of Nursing College at Akura Nanil is near completion while as progress on construction of playfields at Pahalgam, Chandrigam and Panzmulla is under progress. The work on 50MBA Grid Station Wanpoh at an estimated cost of Rs.2.57 crore is near completion and will be inaugurated by 15th of January 2020.The meeting was attended by ADDC, JD Planning, SEs of Hydraulic, PDD, R&B, ACD, Exens of R&B, PDD, PHE, I&FC, Dy. CMO and other concerned.

 

Tags: DDC Anantnag

 

 