LATEST NEWS French Open : Maja Chwalinska beat Anna Kalinskaya to reach maiden Major semi-finals Sukhvinder Singh Sukhu congratulates D.K. Shivakumar on taking oath as Karnataka Chief Minister Media plays a vital role in educating society and promoting positive changes says Kavinder Gupta Nayab Singh Saini’s ‘Go Global’ Approach Gets a New Boost From Women’s Development to Women-Led Development- Modi Government Ushers in a New Era of Governance says Nayab Singh Saini Two Linked Cross-Border Drugs And Arms Smuggling Module Held With 2.2kg Heroin, 6 Pistols Dr. Virendra Kumar Unveils Booklet Showcasing Success Stories of Entrepreneurs Empowered Through Venture Capital Fund and ASIIM Rohit Thakur reviews progress of key education reforms CM Omar Abdullah flags off Cyclothon on World Bicycle Day Kewal Singh Dhillon Takes Charge, BJP Adopts ‘Punjab of Maharaja Ranjit Singh’ as Its Ideal CS Atal Dulloo reviews preparedness for rollout of VB-G RAM G across J&K Why a Diamond Bracelet is the Ultimate Gift for a Woman Jayant Chaudhary Launches ‘Navachar Mantra’, a National Initiative for Grassroots Innovators and Entrepreneurs Special Intensive Revision of Electoral Rolls in Haryana After 24 Years; Door-to-Door Verification Drive to Begin from June 15 D.K. Shivakumar sworn in as Karnataka’s 25th CM Far too less, far too late : Amarinder Singh Raja Warring on Rs 1000 aid to women Mandipalli Ram Prasad Reddy Praises VIT-AP University's Efforts in Hosting the 1st Amaravati International FIDE Rating Chess Tournament Haryana to Construct 26 New Government Ayurvedic Dispensaries Across Six Districts at a Cost of Rs. 15.70 Crore Haryana proposes Rs. 100 Crore Green Climate Fund to Tackle Climate Challenges Mallikarjun Kharge, Rahul Gandhi arrive in K’taka for Shivakumar’s swearing-in ECI hosts global meet on tackling election misinformation, digital challenges

 

Dr. Bilal Mohiud Din Bhat inspects Transit Accommodation for PM package employees at Machbawan

Reviews progress on construction, Allied Works at Machbawan, Shangus, Rambirpora

Dr Bilal Mohi Ud Din Bhat, Anantnag, DC Anantnag, Deputy Commissioner Anantnag, Kashmir, Jammu And Kashmir, Jammu, District Administration Anantnag

Web Admin

Web Admin

5 Dariya News

Anantnag , 09 Mar 2026

Last updated on: Mar 10, 2026, 10:18 IST

To take stock of the ongoing works on PM package Employees Transit Accommodations at Machbawan, Rambirpora and Shangus,  Deputy Commissioner (DC) Anantnag, Dr. Bilal Mohiud Din Bhat, today conducted an extensive tour of these under construction accommodations.

During the visit, the DC reviewed about the progress of the construction and allied works like provision of water supply, electricity, etc at these transit accommodations. Major focus of the visit was the approach road issue at Masbhawan for which the DPR at the cost of Rs. 1.5 Crore has been prepared.

Taking further review of the construction works, the DC issued on-the-spot directions to the concerned executing agencies to expedite the same for timely completion and allotment of the residential quarters.  Speaking on the occasion, the DC said the district administration is committed to ensuring the construction and other works for these accommodations are completed in a time bound manner.

He said the accommodations will come up will all the requisite utilities and essential amenities for convenience of the allottees. The DC was informed that the necessary measures for provision of essential facilities at these accommodations have been in put place for the allottee employees.

It was given out that there is 92% completion of physical work and 50% physical progress has been achieved on allied works for 15 blocks of Machbawan and it is expected to be completed by October-2026. Regarding financial progress, Rs.32 cores expenditure has been achieved on construction work and Rs 3 crores on allied works so far.

In respect of Rambirpora, 94% physical work for 21 blocks has been completed and 65% physical progress has been achieved for allied works so far, with completion expected in October-2026. In financial progress, expenditure of Rs 46 Core for construction and Rs 3.9 Crore on allied works has been achieved so far.

Further, in case of Shangus, the physical progress is 81% for construction of 20 blocks and 45% for allied works with expenditure of Rs 42 Crore and Rs 3.45 Crore on construction and allied works respectively so far. ADC, SE PWD, SE Jal Shakti, Tehsildar Mattan besides officers from PDD and other concerned departments accompanied the Deputy Commissioner.

 

Tags: Dr Bilal Mohi Ud Din Bhat , Anantnag , DC Anantnag , Deputy Commissioner Anantnag , Kashmir , Jammu And Kashmir , Jammu , District Administration Anantnag

 

 