LATEST NEWS Enthusiastic voters’ response marks first day of home voting in Kalakote Sunderbani-AC Home voting conducted for Senior citizens, PwDs in Samba district Postal ballot voting for ‘Absentee voters on Essential Services’ category held in Samba district Manish Tewari is election tourist, voters will give return ticket on June 4: Jitender Pal Malhotra Akanksha Puri Net Worth [April 2024] | 5 Dariya News Fazilka DC Dr Senu Duggal and SSP come out in field to boost wheat lifting from Market Yards Speed up the Lifting Operations to avoid glut, ADC asks Procurement Agencies Governor Shiv Pratap Shukla stresses the need to ensure clean drinking water LPU Engineering Students adjudged as Top Future Space Innovators by ISRO in National Competition Defeat BJP and oppose its election campaign Put serious questions all other contesting parties regarding their promises and performance at under their regimes :CPI (M-L) N.D. Priya Sethi launches door-to-door campaign to mobilize support for Jugal Kishore Sharma Binding humanity in the thread of unity - Manav Ekta Diwas Gurjit Singh Aujla reached Shastri Market to meet businessmen Unique protest of AAP supporters in IPL match - wearing T-shirts with Arvind Kejriwal's photo they raised slogans of 'Mai bhi Kejriwal' AAP gets strengthened in Faridkot and Khadoor Sahib, big jolt to SAD, Congress and BJP! Five families of Basarke Bhaini join Congress from Akali Dal Late Punjabi Singer Amar Singh Chamkila Net Worth In 1980’s | Music Journey & Controversy Youth should vote enthusiastically in the grand festival of democracy - Chief Electoral Officer Anurag Agarwal Haryana Right to Service Commission imposes Rs 20,000 fine on Junior Engineer for service delay ''Engineering is going to become Quantum" : Prof. Arvind, VC, Punjabi University, Patiala List of Actress Jiya Shankar Movies and TV Shows | 5 Dariya News

 

DDC Doda Vishesh Paul Mahajan reviews performance of PWD, progress of NABARD, CRF & other Projects

Doda, Deputy Commissioner Doda, Vishesh Paul Mahajan, Jammu, Kashmir, Jammu And Kashmir, Jammu & Kashmir, District Administration Doda, NABARD, CRF, PWD
Listen to this article

Web Admin

Web Admin

5 Dariya News

Doda , 06 Oct 2022

To review the performance of PWD (R&B) in the execution of works under Capex Budget 2022-23, NABARD, CRF and Languishing Projects, District Development Commissioner Doda Vishesh Paul Mahajan today chaired a meeting of key officials of the department in his office chamber today. 

The meeting was attended by ADDC, Pran Singh; Superintending Engineer PWD, Suresh Kumar; CPO, Suresh Kumar; Ex En Special Sub Division Gandoh, Mushtaq Ahmed; Ex En Doda, Mohd Rafeeq; Ex En Bhaderwah, Tanzeel Ahmed, AEEs and AEs of the department.

It was informed that out of Rs 685.92 lakhs allocation under the Capex Budget-2022-23, Rs 342.96 lakh stand was released to the PWD department for execution of 72   works. “Out of 72 approved works, 53 have been allotted, while 6 works stand completed and 8 works are declared non feasible by the concerned engineers,” the meeting was told.

 The SE informed that expenditure of Rs 271.65 lakh have been made till date, while bills for work done liability of Rs. 70 lakhs  would be submitted shortly in the concerned treasuries for withdrawal in favour of the concerned contractors.

Regarding NABARD funded works, the meeting was informed that a total 22 works were approved in the district out of which 7 have been completed and work on 11 was on. Under CRF, a total of 31 roads were approved of which seven roads have been completed till date, while work on more 19 projects was on. 

About Languishing Projects, the meeting was told that the department took up 33 projects out of which 18 are complete and work on 10 projects is in progress.The DDC asked SE and Ex Ens to personally monitor the quality of the work on ground. 

It was decided in the meeting that the non-feasible works be recommended for foreclosure and funds involved in these works be processed for reallocation.The DDC directed the concerned to ensure 75% physical and financial completion of the works under all schemes by or before 15th of November.

It was instructed that works involving cement work must be completed before 31th of December. Besides, bottlenecks hampering the progress on some of the roads and other projects were discussed in detail in the meeting and DDC directed the Ex Ens to take up the matter with ADCs/ SDMs, and other concerned officers for early resolution of the issues and timely completion of the works. 

He issued clear directions that if after exhausting all the legitimate sources for the resolution of bottlenecks, the work is not taken up, the same works must be processed for foreclosure.DDC also directed the department to ensure that no work is held up or delayed beyond its allotted time of completion by any contractor.

 

Tags: Doda , Deputy Commissioner Doda , Vishesh Paul Mahajan , Jammu , Kashmir , Jammu And Kashmir , Jammu & Kashmir , District Administration Doda , NABARD , CRF , PWD

 

 

related news

 

 

 

Photo Gallery

 

 

Video Gallery

 

 

5 Dariya News RNI Code: PUNMUL/2011/49000
© 2011-2024 | 5 Dariya News | All Rights Reserved
Powered by: CDS PVT LTD