LATEST NEWS Mandal president and dozens of workers left Akali Dal and joined BJP AAP leaders should tell where they raised farmers' questions : Gurjeet Singh Aujla Modi failed farmers, soldiers: Partap Singh Bajwa Amarinder Singh Raja Warring, Energizes Ongoing Campaign In Ludhiana Congress promises guaranteed first job for every fresh graduate : Amarinder Singh Raja Warring Dr. Subhash Sharma kick starts his election campaign after paying obeisance at Takht Sri Kesgarh Sahib and Mata Naina Devi Temple Kunchacko Boban Net Worth 2024 | Unravelling the Net Worth of a Malayalam Cinema Icon Jannat Zubair Net Worth 2024 | From Child Star to Multi-Millionaire 18 Best Ritu Rai Web Series | 5 Dariya News Governor Shiv Pratap Shukla inaugurates International Seminar on Maharishi Dayanand Karnataka SSLC Result 2024: KSEAB 10th Result to be Declared Today Punjab Police Busts Inter-State Weapon Smuggling Racket; Two Held With Six Pistols World Red Cross Day observed at Raj Bhavan DC Kulwant Singh takes the bus route to encourage voters Former Indian Envoy to US Sandhu Catalyzes Rs. 800 Crores Investment Plan for Amritsar’s Economic Development, Says Dr. Sarbjit Singh Sathiala Lok Sabha Elections 2024 : People With Disability (Pwd) Voters To Be Given Wheel Chairs At Each Polling Station Location- Punamdeep Kaur Every Penny Spent on Election Campaign should be accounted for, says Expenditure Observer Shilpi Sinha Expenditure Observer reviews Preparations for General Elections in Chandigarh British Prime Minister Rishi Sunak Volunteers With Go Dharmic Vigilance Bureau arrests Architect for taking Rs 10,000 bribe Lt Governor Manoj Sinha chairs high-level meeting to review functioning of Department of Culture

 

Kudankulam n-plant to be reconnected to grid in five days

Kudankulam n-plant
Listen to this article

Web Admin

Web Admin

5 Dariya News

Chennai , 22 Jan 2016

The Nuclear Power Corporation of India Ltd (NPCIL) is expected to feed power to the southern grid from its 1,000 MW unit at Kudankulam in Tamil Nadu in five days, according to a senior official.The unit which was under annual maintenance shutdown for nearly seven months restarted fission on January 21.The first unit will be connected to the southern grid in another five days after completing tests, R.S.Sundar, site director, Kudankulam Nuclear Power Project (KNPP), told IANS on Friday.According to Power System Operation Corporation Ltd (POSOCO), the Kudankulam nuclear power plant is expected to be connected to the grid on January 24.

"A unit of this size (1,000 MW) after a long shut down takes some time to come back," a senior official at Atomic Energy Regulatory Board (AERB) told IANS on Friday.He said nod is given to restart the fission process only after checking all the parameters of the reactor and other systems.NPCIL is setting up two 1,000 MW atomic power plants at Kudankulam in Tirunelvelli district, around 650 km from here, at an outlay of around Rs.17,000 crore.The first unit attained criticality, which is the beginning of the fission process, in July 2013.

Subsequently it was connected to the southern grid in October 2013.However, commercial power generation began only December 31, 2014.The unit also experienced breakdowns after commercial production started.The unit was shut down in June 2015 for 60 days for refuelling and annual maintenance in June 2015 for 60 days for refuelling and maintenance.

Operating at full capacity, the unit supplies power to Tamil Nadu (562.5 MW), Puducherry (33.5 MW), Kerala (133 MW), Karnataka (221 MW) and Andhra Pradesh (50 MW).The NPCIL skipped several deadlines in restarting the first unit and finally on January 21 the reactor restarted the fission process.

The second 1,000 MW unit at Kudankulam is expected to go critical, or start the fission process, for the first time sometime this year.The fuel has to be loaded into the second reactor.According to AERB official, the results of second unit's commissioning and inspection reports are being studied."After the reports are studied, AERB might lay down some conditions which have to be completed before NPCIL applies for the permission to load the fuel," he said.India will be signing the remaining agreements with Russia for the third and fourth units at Kudankulam, estimated to cost around Rs.40,000 crore. The site work is expected to begin for these two units sometime this year.Negotiations are on with Russia for fifth and sixth units.

 