LATEST NEWS 5 Killed in Ahmedabad Illegal Firecracker Factory Blast Jennifer Winget Ties the Knot with William Ishmael Ashwini Vaishnaw flags off first direct Ramnagar-Dehradun Express train Four Linked To Cross-Border Drug And Arms Smuggling Network Held In Amritsar PM Modi Failed to Answer Punjab’s Real Issues, Chose False Allegations Instead says Baltej Pannu Govt now an enabler, not controller of enterprise : Nirmala Sitharaman Manoj Sinha Attends Chinar Book Festival Jai Krishan Singh Rouri Felicitates Newly Appointed Punjab Government Board Chairpersons Prime Minister's vision of one lakh young leaders is being realised through MY Bharat : Dr. Mansukh Mandaviya India established as a Serious Global Space Power with Vikram-1 Success Kejriwal, Who Sheltered the Tukde-Tukde Gang, Is Now Handing Out Patriotism Certificates says Tarun Chugh CJI Surya Kant launches Comprehensive youth recovery and rehabilitation campaign in Punjab Kavinder Gupta confers medals to meritorious students at 7th Convocation of JUIT Punjab's Dharamkot, Garhshankar Achieve 100% Electoral Records Digitization says Anindita Mitra Rahul Gandhi attacks Centre over Sonam Wangchuk's hospitalisation PM Modi Insulted Sonam Wangchuk in Arrogance says Arvind Kejriwal Dental College Shimla to be renamed as Rajiv Gandhi Dental College says Sukhvinder Singh Sukhu Youth Must Choose Sports and Education, Not Drugs, to Build Viksit Bharat says Nayab Singh Saini Nayab Singh Saini Pays Tribute to Late Gurnam Singh Gurjar Haryana to Double Vocational Education Coverage, Introduce AI and FinTech in Government Schools Sonam Wangchuk's wife seeks to shift activist from Safdarjung hospital

 

Dr. Bilal Mohi-ud-din Bhat reviews Operational and Safety-Related Infrastructure issues at NIFT Campus

Directs time-bound completion of pending works

Dr Bilal Mohi Ud Din Bhat, Budgam, Deputy Commissioner Budgam, DC Budgam, Kashmir, Jammu And Kashmir, Jammu, District Administration Budgam

Web Admin

Web Admin

5 Dariya News

Budgam , 20 Feb 2026

Last updated on: Feb 20, 2026, 17:12 IST

Deputy Commissioner (DC) Budgam, Dr. Bilal Mohi-ud-din Bhat, today chaired a detailed review meeting to assess the operational and safety-related infrastructure issues of NIFT Budgam at DC office complex Budgam to ensure time-bound completion of all pending works.

The DC took stock of the overall physical progress of the campus, which is spread over 132 kanals of land provided by the Government, and comprises 22 planned buildings, of which 19 buildings are substantially complete. He observed that despite significant progress, several critical components remain pending, hindering the full operationalization of the campus.

The DC reviewed agenda-wise issues in detail and issued various directions. While reviewing HVAC Systems, the chair was informed that HVAC systems are malfunctioning in the Administrative Block, Academic Block, Girls’ Hostel, Guest House, Director’s Residence, and Residential Quarters, while installation and commissioning in the Boys’ Hostel remain pending.

The DC directed immediate technical inspection of all HVAC installations, rectification of faults, and time-bound commissioning to ensure proper heating and ventilation facilities across all buildings. He emphasized that given the prevailing climatic conditions, functional HVAC systems are essential for academic functioning and residential comfort.

Regarding the Electrical Sub-Station, the DC was apprised that substation works, including panels, DG sets, and transformers under Packages 2 and 3, are incomplete. The DC directed JK SIDCO and the concerned executing agency to expedite completion of all substation components and ensure reliable and uninterrupted power supply to the campus. 

He instructed that necessary measures, including utilization of the contractor’s security deposits where required, be taken to avoid further delay. Regarding the Sewage Treatment Plant (STP), the meeting was informed that key components such as the main control panel, sludge drying beds, pumps, and recycled water pipelines are yet to be installed and commissioned.

The DC stressed the environmental significance of a fully functional STP and directed immediate installation and commissioning of all pending components to ensure proper wastewater treatment and compliance with environmental norms. He stated that sustainable infrastructure management is a priority and must not be compromised.

 

Tags: Dr Bilal Mohi Ud Din Bhat , Budgam , Deputy Commissioner Budgam , DC Budgam , Kashmir , Jammu And Kashmir , Jammu , District Administration Budgam

 

 