LATEST NEWS Ghulam Nabi Azad Dispels ‘Rumours’ About Being Next LG Of Jammu And Kashmir Punjab’s Govt Hospitals To Have Facilties At Par With Private Hospitals Sea Of People Converges At Patiala During Rally Of Bhagwant Singh Mann And Arvind Kejriwal Lt Governor Manoj Sinha inaugurates 'Cashless Panchayats', adoption of BHIM-UPI mode of transactions in Gram Panchayats of J&K UT Lt Governor Manoj Sinha addresses the UT-level celebration of Gandhi Jayanti; pays tributes to Father of the Nation Lt Governor Manoj Sinha unveils statue of Mahatma Gandhi and a Charkha installation at Civil Secretariat, Srinagar DC Rajouri Vikas Kundal presides over Gram Sabha at Panchayat Saranoo DLSA collaborates with civic bodies to conduct sanitation drives at Kathua, Lakhanpur DC Rajouri Vikas Kundal presides over Grand Function hosted at BHHS to Celebrate Gandhi Jayanti DC Doda Vishesh Paul Mahajan leads Paryavaran Rally organised by Doda Forest Div Dr. Arun Kumar Mehta e- inaugurates Geo-science Museum at SIDCO Budgam Bram Shanker Jimpa honors 24 Gram Panchayats, 23 Schools and 23 Safai Sewaks at State Level function Enthusiastic public Participation marks Swachhta Hi Seva Campaign across District Kishtwar Patnitop-Gouri Kund Eco Trail: Participants traverse Nature's Path to Spiritual Bliss Swachhta Hi Seva events hosted at Jhajjar Kotli Swachhata Hi Seva cleanliness drive conducted in Div Com Office Jammu Lt Governor chairs a high-level meeting on 'Future-Ready Governance' RDD Doda holds massive cleanliness drive across 237 Panchayats DLSA Samba conducts series of activities to promote Swacchta campaign CM Bhagwant Singh Mann And Delhi CM Arvind Kejriwal Pay Floral Tributes To Mahatma Gandhi And Lal Bahadur Shastri On Their Birth Anniversaries Sashastra Seema Bal conducts cleanliness campaign

 

Div Com Ramesh Kumar inspects status of work on Package I & III of Jammu-Akhnoor Road project

Directs NHIDCL to expedite pace by increasing men & Machinery

Jammu, DDC Jammu, Ramesh Kumar, Divisional Commissioner Jammu, Kashmir, Jammu And Kashmir, Jammu & Kashmir
Listen to this article

Web Admin

Web Admin

5 Dariya News

Jammu , 02 Jun 2023

Divisional Commissioner Jammu, Ramesh Kumar on Friday conducted an extensive tour of Akhnoor and inspected the progress of work on Package I and III of Jammu-Akhnoor Road widening Project.

The Div Com took a round of the entire stretch and inspected the work progress on both the packages at several sites including Bhagwati Nagar, Muthi, Domana, Kangrail, Akhnoor and other locations.

He was accompanied by Deputy Commissioner Jammu, Avny Lavasa; Executive Director NHICDL,Col sandeep Sudhera; General Manager (P), NHIDCL, Col. S P S Samgwan; Chief Engineer, JPDCL, Site Engineer NHIDCL, Akash Saluja; concerned Tehsildars, besides the site Engineers of NHIDCL and other concerned officers.

The Executive Director NHIDCL apprised the Div Com about the current status of work on the prestigious road project, besides progress achieved so far and the future work plan.

While giving details, he informed that land acquisition has been completed and work on raising piers for flyover under package 1 from 4th Tawi Bridge to Canal Head is in progress.

The Div Com directed NHIDCL to expedite the pace of work by increasing men and machinery for timely completion of the work of Package 1.While inspecting work on Package 3 at different sites, the Div Com instructed GM NHIDCL to ensure that the adjoining road is connected with proper ramps.

The Div Com directed the GM NHIDCL to expedite the final works of package 3 and ensure its completion within the set timeline.It was further informed that over 73 percent work has been completed under package 3 which is of 20.61 KM length from Ganesh Vihar to Khati Chowk and the work on bridges is in progress.

It was further informed that the land acquisition process has been completed and the land has been provided to executing agencies for smooth execution of the work.

The Div Com also inspected the site for the new bridge over Chenab and was informed that the work on the project has been started.The NHIDCL was directed to be in regular touch with concerned officers of district administration for seeking logistic support and to share the requirement of construction material.

The Div Com asked the NHIDCL to set weekly, monthly targets and expedite the progress of work for timely completion of the 4 laning of Jammu-Akhnoor Road.

 

Tags: Jammu , DDC Jammu , Ramesh Kumar , Divisional Commissioner Jammu , Kashmir , Jammu And Kashmir , Jammu & Kashmir

 

 