LATEST NEWS Mining: Teaser of Singga and Ranjha Vikram Singh Leaves A Benchmark JKTPO Participated in 23rd Edition of IndiaSoft at Pragati Maidan J&K poised to achieve the historic milestone of completing 2 lakh works under MGNREGA Dr Arun Kumar Mehta applauds J&K Admin for completing appointment of around 10000 Lumberdars/ Chowkidars Bhagwant Mann betrayed by hiking power tariff of industry : Sukhbir Singh Badal 8 dead in Indore stepwell accident, rescue operation underway Nirmala Sitharaman slams Congress for encouraging 'foreign interference' AAP launches 'Modi Hatao, Desh Bachao' poster campaign I was wondering why it stopped so early : Gujarat Titans pacer Shivam Mavi recalls his IPL 2023 auction Arvind Kejriwal calls meeting amidst Covid-19 surge in city India's second largest cricket stadium named as Anil Agarwal International Cricket Stadium Jaipur Narendra Modi meets makers of 'The Elephant Whisperers' IPRS Music Day in collaboration with Meta Y.S. Jagan Mohan Reddy meets Amit Shah, urges release of fund for developmental projects Alcoholic man kills wife, daughter in Telangana Popular OTT action thriller series 'Night Agent' renewed for Season 2 Insta launches new collaborative collections feature to save posts shared with friends IPL 2023 : 'Can't wait to see when it's packed', Cameron Green excited to play in Wankhede Stadium The way we are playing at the moment, can win the Ashes comfortably : Ollie Robinson IPL 2023 : Sanjay Manjrekar expects Gujarat Titans to carry the same kind of confidence they had last season Dharmendra Pradhan slams Odisha govt over 'lawlessness'; BJD counters

 

DC Doda Vishesh Paul Mahajan reviews implementation of JJM

Seeks Completion of all ongoing schemes by March end

Doda, Deputy Commissioner Doda, Vishesh Paul Mahajan, Jammu, Kashmir, Jammu And Kashmir, Jammu & Kashmir, District Administration Doda

Web Admin

Web Admin

5 Dariya News

Doda , 01 Feb 2023

District Development Commissioner, Doda Vishesh Paul Mahajan today set March 31, 2023 as deadline for the completion of ongoing Jal Shakti Department schemes.   

District Development Commissioner, who is also Chairman of District Water and Sanitation Mission (DWSM) under Jal Jeevan Mission was reviewing the status of work on the under execution Water Supply Schemes, here in his office chamber.

The Executive Engineers were asked to complete the allotted works physically and financially by March 31st and settle the bottlenecks, if any within a week.  

The DDC also asked the JSD to resolve issues with the Forest department to ensure timely completion of prestigious JJM projects aimed at to provide safe tap water to all households as envisaged in the scheme.

The meeting was informed that out of 185 tendered projects under JJM, 124 projects have been allotted, and work on 106 projects is under execution. 

Regarding the construction of Slow Sand Filtration plants, the meeting was informed that work out of 5 proposed projects, work on  2 has been started on the ground.

The meeting was attended by Chief Planning Officer, SE Jal Shakti, DPO ICDS, Assistant Commissioner Development, ACP DODA, DIO Doda, Principal DIET Doda, CMO Doda, Executive Engineers of JSD and Irrigation Department, AEEs, JEEs, Representative of DFO Doda and other officials of Jal Shakti department.

 

Tags: Doda , Deputy Commissioner Doda , Vishesh Paul Mahajan , Jammu , Kashmir , Jammu And Kashmir , Jammu & Kashmir , District Administration Doda

 

 

related news

 

 

 

Photo Gallery

 

 

Video Gallery

 

 

5 Dariya News RNI Code: PUNMUL/2011/49000
© 2011-2023 | 5 Dariya News | All Rights Reserved
Powered by: CDS PVT LTD