LATEST NEWS 6 Best Jonita D'Cruz Web Series To Watch [List Updated 2024] AAP LS candidate Umesh Makwana filed his nomination papers in the presence of Bhagwant Mann Actress Malaika Arora presents NariFirst Jewel of India Crown to Eesha Agrawal as Empress in Historic Beauty Pageant Gurjit Singh Aujla was warmly welcomed at the railway station, Senior Congress leaders, workers and city residents showered flowers Applying For NEET PG 2024: Essential Steps and Important Dates 'Falahar Grahan Program’ organized at Raj Bhavan LPU Sets World Record with Largest Display of Macarons Samaira Sandhu Credits Yoga for Transforming Her life District Records Wheat Arrival of Over 10,000 MT Rubina Dilaik Net Worth 2024: From Television Star to Bollywood Debut - Net Worth & Beyond CGC’s Biotechnology department organises event on bioentrepreneurship RBU, NMSU sign MoU to forge strategic collaboration Hasta La Vista Fresher and Farewell Party at GJIMT, Mohali 50,000 Strong Punjab Cong Cadre Will Dismantle Bjp: Amarinder Singh Raja Warring Punjab Raj Bhavan celebrates Himachal Pradesh Foundation Day Himachal Day celebrated with fervour University of Leicester and The Apollo University Partner to Revolutionize Global Healthcare I will respect the faith with which the people of 22 villages placed turban on my head: Sanjay Tandon "In Ambala Cantonment, BJP's hardworking force, whose roar reverberates throughout country"-former Home Minister Anil Vij Karan Singh Grover Net Worth: Filmy Career, Hefty Paychecks, and Luxurious Lifestyle Vote for Modi Ji will be Vote for Vishwa Guru Bharat: Devender Singh Rana

 

Div Com inspects progress of work on Jammu-Akhnoor Road project

'Flyover from Canal Head to Ganesh Vihar likely to complete by July end

DDC Jammu, Ramesh Kumar, Divisional Commissioner Jammu, Jammu, Kashmir, Jammu And Kashmir, Jammu & Kashmir, Avny Lavasa
Listen to this article

Web Admin

Web Admin

5 Dariya News

Jammu , 02 Jul 2022

Divisional Commissioner Jammu, Ramesh Kumar  today inspected the progress of work on Jammu-Akhnoor Road widening Project.The Div Com took a round of the entire stretch and inspected the work progress on all the packages at several sites including Canal Head, Patel Nagar, Paloura, Muthi and other locations.

He was accompanied by Deputy Commissioner Jammu Avny Lavasa; General Manager (P), NHIDCL, Col. S P S Samgwan; Chief Engineer Irrigation, concerned SDM, besides senior officers of JPDCL, Jal shakti, site Engineers of NHIDCL and other concerned officers.

The NHIDCL officials apprised the Div Com about the current status of work on the prestigious road project, besides progress achieved so far and the future work plan.While giving details, the GM NHIDCL informed that Detailed Project Report (DPR) for package 1 from 4th Tawi Bridge to Canal Head rotary has been prepared and submitted for approval and the project is likely to be awarded by July 30, 2022.

The Div Com stressed on early start of work on package 1 and instructed the DC Jammu to expedite the land acquisition process and disbursement of compensation besides relocation of Government buildings coming in its alignment. The Div Com also directed NHIDCL and concerned officers to ensure safe utility shifting.

It was informed that 94 percent work on 4.6 KM package 2 from Canal Head to Ganesh Vihar has been completed, while the flyover was at final stage and it would be thrown open for traffic by July end.

The Div Com instructed GM NHIDCL to expedite the pace of work on approach and ramp of elevated road from both the ends. He also emphasized on installation of signages, besides beautification and landscaping of the area under the elevated road portion with proper drainage network.

The Div Com directed GM NHIDCL to expedite the final works of package 2 and ensure its completion by August 15.It was further given out that 56 percent work on 20.61 KM package 3 from Ganesh vihar to Khati Chowk has been completed and the rest of the work was in progress. 

The concerned officers further informed that the land acquisition process has been completed and the same has been provided to executing agencies for smooth execution of work.The Div Com directed NHIDCL to be in regular touch with concerned officers of district administration for every logistic support and share the requirement of construction material.

He further asked the Corporation to set weekly, monthly targets and expedite the progress of work to complete the project within the stipulated time frame.

 

Tags: DDC Jammu , Ramesh Kumar , Divisional Commissioner Jammu , Jammu , Kashmir , Jammu And Kashmir , Jammu & Kashmir , Avny Lavasa

 

 